Parent: #63
Requested experiment: compare the user's 27B model in AIENOS/Omega using CUDA++ on DGX Spark. New first-party experiment code and tests should use seeded .om and reuse existing runtime/benchmark owners. Do not change the live deployment. No measurements are claimed by this issue. Keep checkpoint locations, private traces, credentials and machine-specific details local. Use public/synthetic benchmark fixtures in shared results. Hardware-dependent steps remain NOT_RUN until executed.
Deliver
- Reconcile current baseline/serving/backend qualification work and reuse it; create no second loader, runtime or benchmark harness.
- Resolve the actual 27B artifact and native adapter; prove complete prefill/decode and actual Omega/CUDA++ execution. Record local source/build/backend identities and refuse silent CPU/vendor-engine fallback.
- Freeze prompt token fixtures and numerical/state correctness contract before timing.
- Measure ordinary token steps and supported chain/tree verification sizes. Start draft lengths 0,1,2,4,8,16,31 where supported; explicitly distinguish draft nodes from verification rows including the anchor. Unsupported sizes are NOT_RUN, not zero-cost measurements.
- At 1K and 32K contexts, record draft, verify, commit/rollback, host/policy and preparation time separately, plus full round wall time and peak memory. Synchronize only at required completion boundaries using native APIs; do not introduce a CUDA timing dependency.
- Produce versioned cost tables keyed to model/precision/backend/context and shape. Use repeated samples, preserve raw observations and uncertainty; do not impose a smooth linear cost assumption or copy upstream times.
- Test timing and identity controls: wrong backend, stale cost table, invalid shapes, incomplete completion and malformed timing records must be rejected.
Acceptance
A reproducible qualified base and cost-curve receipt on real Spark, or precise blockers. Synthetic tests may validate the .om runner but cannot establish hardware costs. This gates the live adaptive-policy comparison; policy unit work can proceed on clearly synthetic fixtures.